|
Client:
National Roads Authority |
Consulting
Engineers: Mott Mac Donald EPO |
|
Contractor:
Celtic Roads Group |
Design: The
Reinforced Earth Company |
In May 2004 the Reinforced
Earth Company Ireland Limited was awarded the contract for
the design and supply of Reinforced Earth materials for 9
underpasses on the Dundalk Western By-Pass Project. Seven of
the underpasses were road over road structures and two
structures were road over river.
The Reinforced Abutments (Sub
structure) were comprised of precast cruciform panels with a
Bossage relief pattern. Panels were manufactured using 50 N
concrete with 50% Ground Granulated Blast Furnace Slag. (GGBFS). The Superstructure was
supported by driven 305*305 ‘H’ piles spaced at 3m centres.
The ‘H’ piles were driven until refusal. Plastic pipes 0.6m
in diameter were placed over protruded piles which rose 6.5m
above ground level. The Reinforced Earth abutments were
constructed with straight abutment walls and wings walls
that were curved on a radius of 30m.
Granular 6i/6j backfill was
reinforced by ribbed galvanized steel reinforcing strips.
The reinforcing strips were placed perpendicular to the back
face of the concrete panels and at some locations the
reinforcing strips were splayed around the plastic pipes.
When the 6m high abutment was completed, the last 0.5m of
the steel ‘H’ pile was cast into a 1.1m wide 30m long
pilecap/bankseat.
The centre line of the ‘H’ piles was located 0.85m heading
the front face of the panels. This ensured that the shortest
possible bridge beams were used on this project. The clear
span between the precast concrete panels of the underpass
bridge varied from 10m up to 18m. It took approximately 10
days to construct one abutment. The average surface area of
the abutments was 289m2.
The construction of the 18 Reinforced Earth Abutments with a
panel surface area of 5200m2 were completed within 6 month
including panel and precast coping manufacture. |