|
Structure
Details |
Max. Retained Height : 5m |
Surface area : 4 300m2 |
Completed : 2001 |
|
500m
long double-sided TerraClassTM retaining walls
forming a marina inside Dun Laoghaire Harbour |
|
Client: Dun
Laoghaire Harbour Company |
Project
Consultant: Mouchel |
|
Contractor:
Ascon Ltd |
Design: The
Reinforced Earth Company Ltd |
|
|
As
part of the continuing development of the existing Dun
Laoghaire Harbour, there was a requirement for a 430m long
breakwater. |
|
During the project tender, the main contractor Ascon Ltd
offered an alternative design for the breakwater using the
Reinforced Earth Company TerraClassTM system with
Paraweb soil reinforcements. This alternative demonstrated
significant cost savings over the reinforced concrete
caissons shown in the project tender documents. The
Reinforced Earth Company design was accepted by the client
and Ascon Ltd was awarded the project using the Reinforced
EarthTM TerraClassTM precast concrete
facing panel design. |
|
Construction of the breakwater commenced in the summer of
2000 following the completion of dredging works and placing
of the submerged rock fill core. Construction was
substantially completed by November 2000. |
|
The
construction was performed between tides by starting from
the shore and progressing into the harbour. In this way all
the labour, plant and materials required for construction
travelled along the partially completed breakwater
from a land base.
This procedure
virtually eliminated the need for expensive floating plant.
|
|
The TerraClassTM
breakwater was designed to withstand traffic loading,
diurnal tidal variations and a substantial lateral wave
force from a specified 'design wave'. Furthermore, by using
the synthetic Paraweb soil reinforcement strip and
connection system, potential corrosion difficulties were
eliminated. |
|
This project demonstrates the
suitability and cost savings that can be achieved by using
the Reinforced Earth Company TerraClassTM and
Paraweb reinforcement systems in marine applications. |